Atnaujinta: 2024.11.29 20:18 (GMT+2)
On August 26, 2004 JSC "Liepājas metalurgs" signed a package of
agreements about a large-scale modernisation of steel production unit,
to be launched in September of this year.
The package consists of four documents:
1) letter of intent on construction with a/s "UPB" and with
developer of project design "GIPROMEZ",
2) an agreement with "VAI POMINI" about delivery of steel casting
equipment and
3) a three-party agreement between "VAI", "GIPROMEZ" and "Liepājas
metalurgs" about developing a master plan for the second phase of
reconstruction, including experts' opinion about process modernisation
as well as about assuring the required electric power capacities.
The first modernisation phase will require investment of EUR 11-12
million (a new continuous steel casting equipment will be installed);
the second phase provides for replacing the open-hearth process with
electric furnaces.
Full reconstruction of the steel works requires investment of about EUR
100 million.