AS HARJU ELEKTER
ANNOUNCEMENT
02.12.98
OPENING OF A NEW PRODUCTION BUILDING
On December 4, 1998, a new substations production building will be
opened in the AS Harju Elekter electric devices factory. The
ferroconcrete framed unit-type substations HEKA are planned to
produce in the new building. The production capacity of a new
branch is 200 unit-type substations per year. The main construction
works were conducted by the company itself, including also
different subcontractors. The building was completed during the
time period of June to October 1998. The investments were made in
the amount of 5.5 million EEK, using the company’s own finances and
a loan taken from the LEONIA Bank.
Endel Palla
Chairman of the Management Board